Berths 142-143 Expansion

project at a glance

Location: Los Angeles, CA

Project Dates: 2016

Owner: Port of Los Angeles

Client: Griffith

Sector: Port Infrastructure

Services: Scheduling

Description

Lead scheduler responsible for developing, implementing & managing construction schedule for the roughly $116M Berth 142-143 Backland Improvement Project. The project consists of 15 automated container rail crane blocks. Grade prep, underground utilities, concrete flatwork, rail installation, reefer rack and electrical systems, startup testing and commissioning. Scheduling scope included coordination of multiphase delivery, time impact analysis, delay notifications, delay correspondence.