Fullerton Road Grade Separation

project at a glance

Location: Los Angeles, CA

Project Dates: 2016 - 2018

Owner: Alameda Corridor East - Construction Authority

 

Sector: Transportation/Infrastructure

Services: Scheduling

Description

Performed field layout, kept track of quantities, put together monthly cost report, and looked at schedule to ensure necessary submittals and materials were procured on time. Performed quantity takeoffs in the field to ensure the proper amount of material was ordered. Supervise work being performed in the field. Keep track of quantities to ensure proper payment is received each month. Create a Labor Distribution Report weekly to keep track of production rates. Create work plans for field crews. Compiled necessary details to properly price out multiple Change Orders, including estimating quantities, reconciling disputed quantities, and gathering pricing from subcontractors to perform work.